The project was carried out into different phases:

  1. In a first phase the dwelling house was renovated.
  2. In a second phase the barn and the cattle sheds were restored and transformed. The outer jacket of the building was stabilized, the principal flagstone as well as the roof were replaced. The sanitary facilities of the house are operational.
  3. The third phase consisted in restructuring the hangar and of construction the dormitories as well as the installation of the neighbourhoods, the camp and the garden

All this work were carried out under the monitoring of a specialized architect charged by the Foundation, as well as various offices of engineers.